Where the $157.25 goes, line by line
Cushman & Wakefield breaks its East Rutherford figure into nine trades. Pricing reflects December 2025 (Office Fit Out Cost Guide 2026).
| Trade | Per sq ft |
|---|---|
| Mechanical, plumbing and fire protection | $28.76 |
| Electrical | $27.40 |
| Doors, frames and hardware | $21.51 |
| Drywall, acoustic ceilings and carpentry | $18.93 |
| General requirements, general conditions and fee | $18.86 |
| Contingency (10%) | $12.20 |
| Architectural millwork | $11.73 |
| General finishes | $11.70 |
| Miscellaneous architectural trades | $6.16 |
| Total | $157.25 |
Mechanical, plumbing, fire protection and electrical together are more than a third of the total. That is why the building's existing systems matter so much in second-generation space.

On the logistics office fit-out, our scope was the open-plan layout, the private offices, paint with the accent wall, and the flooring.
The all-in number: what the per-square-foot figure leaves out
Cushman & Wakefield's figure is construction only. It leaves out low-voltage cabling, audio-visual equipment, security, furniture and soft costs. For Tier 2 markets, East Rutherford among them, the guide adds these ranges:
| On top of construction | Per sq ft |
|---|---|
| Soft costs11% of hard cost | $15.15–$22.72 |
| IT4% of hard cost | $5.51–$8.26 |
| Audio-visual12% of hard cost | $16.53–$24.79 |
| Furniture20% of hard cost | $27.54–$41.32 |
| Miscellaneous2% of hard cost | $2.75–$4.13 |
Added to the $157.25 construction figure, that is $224.73 to $258.47 a square foot all-in. For a 2,500 sq ft office: $561,825 to $646,175, before any allowance from the landlord.
Retail fit-out cost: storefronts and shops
Cushman & Wakefield prices offices only. For retail, Terrapin Construction Group's July 2026 benchmarks give hard costs for second-generation space in an average shell (Terrapin):
- Northeast, mid-tier retail (New York, New Jersey, Massachusetts, Connecticut): $135 to $215 a square foot.
- Northeast, basic retail: about $81 to $129, using Terrapin's own 0.6 multiplier for basic retail in the same market.
- U.S. ranges: basic retail $40 to $90, mid-tier $90 to $180, premium $150 to $300.
- A 1,500 sq ft mid-tier shop in the Northeast: $202,500 to $322,500 in hard costs.
What the landlord hands over changes the number by 30% to 50% for the same use, Terrapin says. What the tenant adds, per square foot, by the condition of the space:
| Space handed over as | Tenant adds |
|---|---|
| Cold dark shellBare structure: no HVAC, electrical distribution, plumbing or restroom, often no slab finish. | $60–$130 |
| Gray shellUtilities stubbed to the space. Distribution, HVAC and restrooms are the tenant's. | $45–$100 |
| White boxFinished walls and ceiling, basic lighting, HVAC in place, a working restroom. | $30–$80 |
| Vanilla shellA white box plus flooring, a finished restroom and typically a code-compliant entry. | $20–$60 |

On the storefront door job, we measured and prepared the existing opening, fitted the door and trimmed it at the brick. A storefront is part of the building's entrance, which is also where accessibility upgrades start (see below).
The tenant improvement allowance, and who pays what
A tenant improvement allowance is a pre-negotiated sum from the landlord toward the fit-out, usually quoted per square foot. It typically covers walls and ceilings, electrical work, flooring and paint. Furniture and other items not permanently attached are usually left out (Cushman & Wakefield).
- Office leases with longer terms: $30 to $90 a square foot (Terrapin, Q3 2026).
- Second-generation retail in a Class B center: $15 to $35. First-generation retail: $30 to $60.
- Retail allowances tightened by 8% to 15% in core markets over the first half of 2026, as landlords repriced their concessions.
- Who pays: both, in the shares the lease sets. The landlord gives the allowance and sometimes free rent; the tenant pays the rest.
Worked for a 2,500 sq ft office at the East Rutherford figure: construction is $393,125. An allowance of $30 to $90 a square foot covers $75,000 to $225,000. That leaves the tenant $168,125 to $318,125, before furniture, IT and soft costs.
Three New Jersey points belong in the lease too. The permit stays the owner's property, and a tenant or contractor who applies needs the owner's affidavit (N.J.A.C. 5:23-2.15(d)). Only the property owner can issue the sales tax certificate for the work (Form ST-8). Settle who signs each before work is priced.
New Jersey permits for a Group B or Group M fit-out
The building code sorts every space by use. Offices and professional services are Business, Group B. Shops where the public buys merchandise are Mercantile, Group M (IBC 2024, sections 304.1 and 309.1). The 2024 codes took effect in New Jersey on August 17, 2026 (R.2026 d.086); our page on the 2024 code change explains the grace period. The permit runs in this order:
- The application names the use group and the estimated cost of the work, including built-in finishes (N.J.A.C. 5:23-2.15(a)).
- Plans carry the seal and signature of the registered architect or licensed engineer who prepared them, on every sheet (5:23-2.15(f)1ix). We work with the owner's architect, or provide the drawings ourselves.
- The owner, or the owner's agent, architect or contractor, applies. Anyone other than the owner files the owner's affidavit with it (5:23-2.15(d)).
- In a multi-tenant building, a tenant space needs its own permit when the tenant does the fit-up, or uses a different architect or contractors from the base building (5:23-2.23A).
- Plumbing, electrical and HVAC work is done only by people licensed for it, and their seal goes on each subcode application (5:23-2.15(b)2).
- The construction office has 20 business days to approve or deny a complete application, and 7 business days for corrected plans (5:23-2.16).
- Each inspection is requested at least 24 hours ahead and done within three business days (5:23-2.18).
- The certificate of occupancy is issued within 10 business days of a written application (5:23-2.23(j)). Changing a space's use without one first is unlawful, and the space must meet the rehabilitation subcode (5:23-2.6(b)).
New Jersey's home improvement contractor registration covers work on homes, use groups R-2 to R-5 (5:23-2.15(b)8i). For an office or a shop, ask who holds the plumbing, electrical and HVAC licenses on the job.
The permit fee, worked for a Belleville office
Fees are set by each town. In Belleville, alterations are $28 per $1,000 of estimated cost, with an $85 minimum. Plan review is 25% of the permit fee, paid before the plans are reviewed (Belleville Code § 12-1.3). The state adds a training fee of $1.90 per $1,000 (N.J.A.C. 5:23-4.19(b)). For the $393,125 office:
- Building permit fee: $11,007.50
- Plan review, 25% of that fee, paid first: $2,751.88
- State training fee: $746.94
Electrical work has its own fee lines in the same section of the code. Other towns in Essex County set their own fees.
Accessibility: the barrier-free items a fit-out pays for
New Jersey's rehabilitation subcode decides what an alteration must fix. When a primary function space is altered, the route to it has to be made accessible, up to the point where that costs more than 20% of the alteration (N.J.A.C. 5:23-6.6(k)). The route includes parking, the entrance, the way in, restrooms, drinking fountains and telephones. On the $393,125 office, that is up to $78,625.
- Restrooms. Moving toilet partitions brings an accessible stall where it fits without moving fixtures. Replacement fixtures and hardware must meet ICC A117.1 (5:23-6.6(e)2).
- Reconfigured space. New layouts meet the code's accessibility chapter, to the maximum extent feasible (5:23-6.6(e)3).
- Doors. New or enlarged door openings get doors that meet ICC A117.1 section 404 (5:23-6.6(e)4).
- Lighting. Replacing a whole lighting system brings it up to the commercial energy code (5:23-6.6(e)21).
- Carpet. Carpet that fails the federal "pill test" for flammability may not be used (5:23-6.6).
The federal ADA works the same way. Moving walls, adding a sales counter or display shelves, changing an entrance, or replacing fixtures, flooring or carpet is an alteration; painting and wallpapering are not (ADA.gov). A business with 30 or fewer full-time employees, or $1 million or less in revenue, can claim the Disabled Access Credit (Section 44). Businesses of any size can deduct up to $15,000 a year for removing barriers (Section 190).

The costs that surface after the walls open
Terrapin names the overruns it sees most, and most are code triggers, not design choices (2026, U.S.):
- Accessible path of travel: $15 to $60 a square foot of the area affected.
- Energy code: $8 to $25 a square foot when new lighting or HVAC pulls insulation and glazing into the job.
- A bigger electrical service: $35,000 to $180,000, and months more if the utility is involved.
- Sprinkler heads moved: $4 to $12 a square foot of the area affected, plus 4 to 8 weeks of permit time. Wall and ceiling changes almost always require it.
Ceilings are where much of this meets. Our drop ceiling cost guide covers office grids with lay-in lights and sprinkler tiles.
How long an office or retail fit-out takes
- Design and drawings. On our commercial jobs this is the retainer phase: site review, drawings and permit submissions, before the construction price is final.
- Permit review. 20 business days for a complete application in New Jersey, plus 7 for each set of corrected plans. Terrapin says permitting adds 4 to 12 weeks, depending on the town and on accessibility or energy code review.
- Construction. A retail fit-out runs 8 to 16 weeks from permit to certificate of occupancy in Terrapin's 2026 benchmark.
- Materials. Standard finishes and fixtures are back to 4 to 6 weeks. For a new electrical service, Terrapin still plans a 90-day buffer for equipment.
- Inspections and the certificate. Each inspection within three business days of the request; the certificate of occupancy within 10 business days of applying.

Sales tax on a commercial fit-out in New Jersey
Most fit-out labor is a capital improvement, which New Jersey does not tax, but only with the paperwork in place:
- Form ST-8. "May be issued only by the owner of the real property." Without a completed one, a registered contractor must collect tax on the labor (ST-8). On a leased space, that means the landlord.
- Materials. The contractor pays tax when buying them, and the ST-8 cannot be used for materials.
- Taxed even with an ST-8: installing carpet and other flooring, and installing a hard-wired security, burglar or fire alarm system.
- Signs. Installing a permanently affixed sign has been taxable since October 1, 2022. The rate is 6.625% (Tax Topic Bulletin S&U-3).
How a fit-out runs with us
We deal with the architect, the building department, the suppliers and the licensed trades, so the owner or tenant deals with one contractor.
- Retainer and site review: we measure the space, confirm what the business needs and bring in the architect.
- Drawings and permits: plans, trade drawings and the submissions to the town's construction office.
- Build: demolition, framing, rough plumbing and electrical, fire protection, then finishes.
- Inspections and turnover: the trade and final inspections, then handover.
Every commercial account starts with a retainer for the design and permit phase. On large projects we can take a smaller deposit with more frequent payments tied to completed work. Change orders are due at completion, and financing is available on commercial work. Ask Andrew about current terms.
Where we build out offices and storefronts
From our office at 65 Newark Ave, Unit 1 in Belleville, across all 22 Essex County towns: Belleville, Bloomfield, Glen Ridge, East Orange, Nutley, Orange, Montclair, Newark, West Orange, Verona, Irvington, South Orange, Cedar Grove, Essex Fells, Maplewood, Caldwell, North Caldwell, Roseland, West Caldwell, Livingston, Millburn, Fairfield. We also work in Union and Passaic counties.