What an office or retail fit-out costs in New Jersey

A full office fit-out in East Rutherford costs $157.25 a square foot in Cushman & Wakefield's 2026 guide, its only New Jersey market. Reworking an existing office runs 10% to 15% less: $133.66 to $141.53. A cosmetic refresh is $40 to $75 a square foot in 2026 national figures.

Those are market figures, not an AB quote. Below: the three levels of fit-out, what 1,500 to 10,000 sq ft comes to, retail space, the landlord's allowance, New Jersey permits, accessibility, timing and sales tax. Office fit-outs and storefronts are part of our commercial construction work. Restaurants have their own build-out cost guide.

Published November 17, 2026 by AB Contracting & Design LLC, Belleville, NJ. N.J. HIC Reg. #13VH11431800. Market prices and New Jersey rules come from the sources linked below, read on the day of publishing.

Office suite mid-renovation behind a glass wall, with ceiling tiles pulled down, debris across the floor and a wooden stepladder, seen from a finished lobby corridor
An office suite stripped mid-renovation behind its glass front. A stock photo, not an AB job. Photo: Shuaizhi Tian, Pexels.

Three nearby markets, read side by side

East Rutherford, NJ
$157.25 a sq ftUp from $155.27 in 2025, down from $161.49 in 2024 (Cushman & Wakefield, 2026).
Philadelphia
$169.64 a sq ftThe same office, priced the same way, across the river from South Jersey.
New York City
$220.62 a sq ft$63 a square foot more than East Rutherford, 40% higher.

Office fit-out cost per square foot, by level of work

How much of the space changes decides the price more than anything else. Three levels, each with its source. None is a quote from us.

Office fit-out cost per square foot by level of work, 2026 market figures
Level of workPer sq ft
Light refreshPaint, carpet tile, new light fixtures and minor millwork; the walls stay where they are. Axenia Construction, September 2026, U.S. figure.$40–$75
Second-generation reworkA new layout in an office a previous tenant built out: selective demolition, then reusing 25% of the walls and ceilings, part of the ductwork, all of the main electrical distribution and a quarter of the power and lighting wiring. East Rutherford, 10% to 15% below a full fit-out.$133.66–$141.53
Full build-outEverything new: private offices, workstations, reception and conference rooms. East Rutherford, 2026, with a 10% contingency included. Clearing out an old fit-out first adds demolition.$157.25

Second-generation space looks like the bargain, and often is not. Terrapin Construction Group warns that the electrical service, the HVAC tonnage and the restroom count are too small for the new use roughly 40% to 60% of the time (Terrapin, July 2026). Have them checked before the lease is signed.

What an office build-out comes to at four sizes

The three levels above, applied to common office sizes. The multiplication is ours; the per-square-foot figures are the sources'. Construction only: furniture, IT and design come after this table.

Office fit-out cost at four sizes, by level of work, 2026 market figures
OfficeFull build-out at $157.25
1,500 sq ft$235,875Second-generation: $200,490–$212,295Light refresh: $60,000–$112,500
2,500 sq ft$393,125Second-generation: $334,150–$353,825Light refresh: $100,000–$187,500
5,000 sq ft$786,250Second-generation: $668,300–$707,650Light refresh: $200,000–$375,000
10,000 sq ft$1,572,500Second-generation: $1,336,600–$1,415,300Light refresh: $400,000–$750,000

Where the $157.25 goes, line by line

Cushman & Wakefield breaks its East Rutherford figure into nine trades. Pricing reflects December 2025 (Office Fit Out Cost Guide 2026).

East Rutherford office fit-out cost by trade, per square foot, Cushman & Wakefield 2026
TradePer sq ft
Mechanical, plumbing and fire protection$28.76
Electrical$27.40
Doors, frames and hardware$21.51
Drywall, acoustic ceilings and carpentry$18.93
General requirements, general conditions and fee$18.86
Contingency (10%)$12.20
Architectural millwork$11.73
General finishes$11.70
Miscellaneous architectural trades$6.16
Total$157.25

Mechanical, plumbing, fire protection and electrical together are more than a third of the total. That is why the building's existing systems matter so much in second-generation space.

Finished office fit-out with blue accent wall, workstation cubicles, carpet tile and drop ceiling lighting
Our job: a logistics office fit-out with workstation pods, private offices along the wall, carpet tile and a dark blue accent wall.

On the logistics office fit-out, our scope was the open-plan layout, the private offices, paint with the accent wall, and the flooring.

The all-in number: what the per-square-foot figure leaves out

Cushman & Wakefield's figure is construction only. It leaves out low-voltage cabling, audio-visual equipment, security, furniture and soft costs. For Tier 2 markets, East Rutherford among them, the guide adds these ranges:

Costs on top of an office fit-out, Tier 2 markets, Cushman & Wakefield 2026
On top of constructionPer sq ft
Soft costs11% of hard cost$15.15–$22.72
IT4% of hard cost$5.51–$8.26
Audio-visual12% of hard cost$16.53–$24.79
Furniture20% of hard cost$27.54–$41.32
Miscellaneous2% of hard cost$2.75–$4.13

Added to the $157.25 construction figure, that is $224.73 to $258.47 a square foot all-in. For a 2,500 sq ft office: $561,825 to $646,175, before any allowance from the landlord.

Retail fit-out cost: storefronts and shops

Cushman & Wakefield prices offices only. For retail, Terrapin Construction Group's July 2026 benchmarks give hard costs for second-generation space in an average shell (Terrapin):

  • Northeast, mid-tier retail (New York, New Jersey, Massachusetts, Connecticut): $135 to $215 a square foot.
  • Northeast, basic retail: about $81 to $129, using Terrapin's own 0.6 multiplier for basic retail in the same market.
  • U.S. ranges: basic retail $40 to $90, mid-tier $90 to $180, premium $150 to $300.
  • A 1,500 sq ft mid-tier shop in the Northeast: $202,500 to $322,500 in hard costs.

What the landlord hands over changes the number by 30% to 50% for the same use, Terrapin says. What the tenant adds, per square foot, by the condition of the space:

What a tenant adds by shell condition, per square foot, Terrapin 2026
Space handed over asTenant adds
Cold dark shellBare structure: no HVAC, electrical distribution, plumbing or restroom, often no slab finish.$60–$130
Gray shellUtilities stubbed to the space. Distribution, HVAC and restrooms are the tenant's.$45–$100
White boxFinished walls and ceiling, basic lighting, HVAC in place, a working restroom.$30–$80
Vanilla shellA white box plus flooring, a finished restroom and typically a code-compliant entry.$20–$60
New full-view glass overhead door installed in the same brick storefront opening
Our job: a brick storefront's window opening refitted with a full-view glass overhead door.

On the storefront door job, we measured and prepared the existing opening, fitted the door and trimmed it at the brick. A storefront is part of the building's entrance, which is also where accessibility upgrades start (see below).

The tenant improvement allowance, and who pays what

A tenant improvement allowance is a pre-negotiated sum from the landlord toward the fit-out, usually quoted per square foot. It typically covers walls and ceilings, electrical work, flooring and paint. Furniture and other items not permanently attached are usually left out (Cushman & Wakefield).

  • Office leases with longer terms: $30 to $90 a square foot (Terrapin, Q3 2026).
  • Second-generation retail in a Class B center: $15 to $35. First-generation retail: $30 to $60.
  • Retail allowances tightened by 8% to 15% in core markets over the first half of 2026, as landlords repriced their concessions.
  • Who pays: both, in the shares the lease sets. The landlord gives the allowance and sometimes free rent; the tenant pays the rest.

Worked for a 2,500 sq ft office at the East Rutherford figure: construction is $393,125. An allowance of $30 to $90 a square foot covers $75,000 to $225,000. That leaves the tenant $168,125 to $318,125, before furniture, IT and soft costs.

Three New Jersey points belong in the lease too. The permit stays the owner's property, and a tenant or contractor who applies needs the owner's affidavit (N.J.A.C. 5:23-2.15(d)). Only the property owner can issue the sales tax certificate for the work (Form ST-8). Settle who signs each before work is priced.

New Jersey permits for a Group B or Group M fit-out

The building code sorts every space by use. Offices and professional services are Business, Group B. Shops where the public buys merchandise are Mercantile, Group M (IBC 2024, sections 304.1 and 309.1). The 2024 codes took effect in New Jersey on August 17, 2026 (R.2026 d.086); our page on the 2024 code change explains the grace period. The permit runs in this order:

  1. The application names the use group and the estimated cost of the work, including built-in finishes (N.J.A.C. 5:23-2.15(a)).
  2. Plans carry the seal and signature of the registered architect or licensed engineer who prepared them, on every sheet (5:23-2.15(f)1ix). We work with the owner's architect, or provide the drawings ourselves.
  3. The owner, or the owner's agent, architect or contractor, applies. Anyone other than the owner files the owner's affidavit with it (5:23-2.15(d)).
  4. In a multi-tenant building, a tenant space needs its own permit when the tenant does the fit-up, or uses a different architect or contractors from the base building (5:23-2.23A).
  5. Plumbing, electrical and HVAC work is done only by people licensed for it, and their seal goes on each subcode application (5:23-2.15(b)2).
  6. The construction office has 20 business days to approve or deny a complete application, and 7 business days for corrected plans (5:23-2.16).
  7. Each inspection is requested at least 24 hours ahead and done within three business days (5:23-2.18).
  8. The certificate of occupancy is issued within 10 business days of a written application (5:23-2.23(j)). Changing a space's use without one first is unlawful, and the space must meet the rehabilitation subcode (5:23-2.6(b)).

New Jersey's home improvement contractor registration covers work on homes, use groups R-2 to R-5 (5:23-2.15(b)8i). For an office or a shop, ask who holds the plumbing, electrical and HVAC licenses on the job.

The permit fee, worked for a Belleville office

Fees are set by each town. In Belleville, alterations are $28 per $1,000 of estimated cost, with an $85 minimum. Plan review is 25% of the permit fee, paid before the plans are reviewed (Belleville Code § 12-1.3). The state adds a training fee of $1.90 per $1,000 (N.J.A.C. 5:23-4.19(b)). For the $393,125 office:

  • Building permit fee: $11,007.50
  • Plan review, 25% of that fee, paid first: $2,751.88
  • State training fee: $746.94

Electrical work has its own fee lines in the same section of the code. Other towns in Essex County set their own fees.

Accessibility: the barrier-free items a fit-out pays for

New Jersey's rehabilitation subcode decides what an alteration must fix. When a primary function space is altered, the route to it has to be made accessible, up to the point where that costs more than 20% of the alteration (N.J.A.C. 5:23-6.6(k)). The route includes parking, the entrance, the way in, restrooms, drinking fountains and telephones. On the $393,125 office, that is up to $78,625.

  • Restrooms. Moving toilet partitions brings an accessible stall where it fits without moving fixtures. Replacement fixtures and hardware must meet ICC A117.1 (5:23-6.6(e)2).
  • Reconfigured space. New layouts meet the code's accessibility chapter, to the maximum extent feasible (5:23-6.6(e)3).
  • Doors. New or enlarged door openings get doors that meet ICC A117.1 section 404 (5:23-6.6(e)4).
  • Lighting. Replacing a whole lighting system brings it up to the commercial energy code (5:23-6.6(e)21).
  • Carpet. Carpet that fails the federal "pill test" for flammability may not be used (5:23-6.6).

The federal ADA works the same way. Moving walls, adding a sales counter or display shelves, changing an entrance, or replacing fixtures, flooring or carpet is an alteration; painting and wallpapering are not (ADA.gov). A business with 30 or fewer full-time employees, or $1 million or less in revenue, can claim the Disabled Access Credit (Section 44). Businesses of any size can deduct up to $15,000 a year for removing barriers (Section 190).

Finished commercial restroom with white subway tile wainscot, wall-hung sink and urinal
Our job: a commercial restroom redone with white subway tile wainscot, a wall-hung sink and a urinal.

The costs that surface after the walls open

Terrapin names the overruns it sees most, and most are code triggers, not design choices (2026, U.S.):

  • Accessible path of travel: $15 to $60 a square foot of the area affected.
  • Energy code: $8 to $25 a square foot when new lighting or HVAC pulls insulation and glazing into the job.
  • A bigger electrical service: $35,000 to $180,000, and months more if the utility is involved.
  • Sprinkler heads moved: $4 to $12 a square foot of the area affected, plus 4 to 8 weeks of permit time. Wall and ceiling changes almost always require it.

Ceilings are where much of this meets. Our drop ceiling cost guide covers office grids with lay-in lights and sprinkler tiles.

How long an office or retail fit-out takes

  • Design and drawings. On our commercial jobs this is the retainer phase: site review, drawings and permit submissions, before the construction price is final.
  • Permit review. 20 business days for a complete application in New Jersey, plus 7 for each set of corrected plans. Terrapin says permitting adds 4 to 12 weeks, depending on the town and on accessibility or energy code review.
  • Construction. A retail fit-out runs 8 to 16 weeks from permit to certificate of occupancy in Terrapin's 2026 benchmark.
  • Materials. Standard finishes and fixtures are back to 4 to 6 weeks. For a new electrical service, Terrapin still plans a 90-day buffer for equipment.
  • Inspections and the certificate. Each inspection within three business days of the request; the certificate of occupancy within 10 business days of applying.
Seafood market interior during fit-out with display cases and prep equipment being set
Our job: a seafood market mid fit-out, with display cases and prep equipment being set.

Sales tax on a commercial fit-out in New Jersey

Most fit-out labor is a capital improvement, which New Jersey does not tax, but only with the paperwork in place:

  • Form ST-8. "May be issued only by the owner of the real property." Without a completed one, a registered contractor must collect tax on the labor (ST-8). On a leased space, that means the landlord.
  • Materials. The contractor pays tax when buying them, and the ST-8 cannot be used for materials.
  • Taxed even with an ST-8: installing carpet and other flooring, and installing a hard-wired security, burglar or fire alarm system.
  • Signs. Installing a permanently affixed sign has been taxable since October 1, 2022. The rate is 6.625% (Tax Topic Bulletin S&U-3).

How a fit-out runs with us

We deal with the architect, the building department, the suppliers and the licensed trades, so the owner or tenant deals with one contractor.

  1. Retainer and site review: we measure the space, confirm what the business needs and bring in the architect.
  2. Drawings and permits: plans, trade drawings and the submissions to the town's construction office.
  3. Build: demolition, framing, rough plumbing and electrical, fire protection, then finishes.
  4. Inspections and turnover: the trade and final inspections, then handover.

Every commercial account starts with a retainer for the design and permit phase. On large projects we can take a smaller deposit with more frequent payments tied to completed work. Change orders are due at completion, and financing is available on commercial work. Ask Andrew about current terms.

Where we build out offices and storefronts

From our office at 65 Newark Ave, Unit 1 in Belleville, across all 22 Essex County towns: Belleville, Bloomfield, Glen Ridge, East Orange, Nutley, Orange, Montclair, Newark, West Orange, Verona, Irvington, South Orange, Cedar Grove, Essex Fells, Maplewood, Caldwell, North Caldwell, Roseland, West Caldwell, Livingston, Millburn, Fairfield. We also work in Union and Passaic counties.

Every town we serve

Office and retail fit-out cost questions

How much does an office build-out cost per square foot in New Jersey?

Cushman & Wakefield's 2026 guide puts a full office fit-out in East Rutherford, its only New Jersey market, at $157.25 a square foot, with a 10% contingency included. Reworking an existing office runs 10% to 15% less, about $133.66 to $141.53. A cosmetic refresh is $40 to $75 in 2026 national figures. These are market figures, not an AB quote.

How much does it cost to build out 2,500 square feet of office space?

At the East Rutherford figure, $393,125 for the construction. Furniture, IT, audio-visual and soft costs add $67.48 to $101.22 a square foot in the same guide, so the all-in figure is $561,825 to $646,175. A landlord's allowance comes off the tenant's share.

What is a tenant improvement allowance, and who pays for the build-out?

A tenant improvement allowance is a sum the landlord agrees to put toward the fit-out, usually quoted per square foot (Cushman & Wakefield). Terrapin Construction Group's Q3 2026 benchmark for office leases with longer terms is $30 to $90 a square foot. Both sides pay, in shares the lease sets: the landlord's allowance first, the tenant the rest.

Do I need a permit for an office or retail fit-out in New Jersey?

Yes, for anything beyond cosmetic work. The application names the use group (B for offices, M for retail) and the estimated cost, plans carry an architect's or engineer's seal, and licensed trades sign their own subcode applications (N.J.A.C. 5:23-2.15). A tenant doing its own fit-up in a multi-tenant building needs a separate permit for its space (5:23-2.23A).

Does an office renovation trigger ADA upgrades in New Jersey?

Often. When a primary function space is altered, New Jersey's rehabilitation subcode requires an accessible path of travel to it, up to 20% of the alteration cost (N.J.A.C. 5:23-6.6(k)). Under the federal ADA, moving walls or replacing flooring is an alteration; painting is not.

How long does a commercial fit-out take?

Plan for design and permits, then construction. New Jersey gives the construction office 20 business days to decide on a complete application (N.J.A.C. 5:23-2.16). Terrapin's 2026 benchmark puts a retail fit-out at 8 to 16 weeks from permit to certificate of occupancy, with permitting adding 4 to 12 weeks.

Is a commercial fit-out taxed in New Jersey?

Labor on a capital improvement is exempt when the property owner gives the contractor Form ST-8; only the owner of the real property can issue it. Installing carpet or other flooring, hard-wired alarm systems and permanently affixed signs stays taxable at 6.625% even then. The contractor pays tax on materials either way.

What is the difference between first-generation and second-generation office space?

First-generation space has never been built out, so everything is new. Second-generation space was fitted out by a previous tenant. Cushman & Wakefield's adaptive-reuse model keeps part of the walls, ceilings, sprinkler heads and ductwork, all of the main electrical distribution and a quarter of the power and lighting wiring, for 10% to 15% less.

Do you do office and retail fit-outs?

Yes. Our commercial work includes office fit-outs (partitions, ceilings, lighting, flooring and paint), retail storefronts, entries and glass overhead doors, and commercial restrooms. We have not published a fit-out price, which is why the figures on this page are market figures. Phone estimates are free; an in-person estimate is $50, and it comes off your contract when you sign.

Sources

  1. Cushman & Wakefield, Office Fit Out Cost Guide 2026, Americas

    East Rutherford, Philadelphia and New York City by trade, 2024 to 2026; Generation 1 and 2 scope; Tier 2 add-on ranges. Pricing as of December 2025. Also the guide's U.S. page.

  2. Cushman & Wakefield, Office Fit-Out Costs Across the Americas Rise 5.5%

    Americas and U.S. averages, Northeast and Tri-State, contractor survey, electrical share. March 24, 2026.

  3. Cushman & Wakefield, Everything you need to know about Tenant Improvement Allowance

    What an allowance is, what it usually covers and leaves out.

  4. Terrapin Construction Group, Tenant Improvement Cost Per Square Foot

    Retail and office ranges, Northeast retail, shell condition, allowance benchmarks, who pays, code-triggered costs and timing. Published March 30, 2026, updated July 2026.

  5. Axenia Construction, Office Renovation Cost

    Cosmetic refresh range per square foot. September 4, 2026.

  6. International Building Code 2024, Chapter 3

    Section 304.1, Business Group B; section 309.1, Mercantile Group M.

  7. N.J. Department of Community Affairs, adoption of the 2024 model codes, R.2026 d.086

    Adopted July 15, 2026, effective August 17, 2026.

  8. N.J.A.C. 5:23-2.15, construction permit applications

    Use group and estimated cost (a); licensed trades (b)2; home improvement (b)8i; who applies (d); sealed plans (f)1ix.

  9. N.J.A.C. 5:23-2.23A, multi-tenant buildings

    When a tenant space needs its own permit.

  10. N.J.A.C. 5:23-2, administration and enforcement (DCA text)

    Change of use 2.6(b); permit review clock 2.16; inspections 2.18; certificate of occupancy 2.23(j).

  11. N.J.A.C. 5:23-6.6, rehabilitation subcode, alterations

    Path of travel and the 20% rule (k); restrooms, reconfigured space, doors, lighting (e); carpet.

  12. Township of Belleville Code, Chapter 12, § 12-1.3 Fees

    Alteration fee per $1,000, the $85 minimum and the 25% plan review fee.

  13. N.J.A.C. 5:23-4.19, state training fee

    Subsection (b): $1.90 per $1,000 of construction value.

  14. ADA.gov, ADA Update: A Primer for Small Business

    What counts as an alteration; Section 44 credit and Section 190 deduction. July 29, 2026.

  15. N.J. Division of Taxation, Form ST-8, Certificate of Exempt Capital Improvement

    Owner-only certificate; work that stays taxable.

  16. N.J. Division of Taxation, Tax Topic Bulletin S&U-3, Contractors and New Jersey Taxes

    Capital improvements, sign installation, the 6.625% rate.