Does your project need a permit? Look it up
It's unlawful to build, enlarge, repair, renovate, alter or demolish a structure without a permit unless the code makes an exception (N.J.A.C. 5:23-2.14). The table sorts common home projects into the code's own groups:
- No permit. Ordinary maintenance (5:23-2.7) or a job the code exempts. No application, and for ordinary maintenance no notice and no inspection.
- Start on notice. Minor work (5:23-2.17A). Tell the office before work begins, in person or electronically, then file the application within five business days. It still gets inspected.
- Permit first. No work until the permit is issued.
- Permit. Ask about notice. The job is outside ordinary maintenance, and whether it fits minor work depends on the details. Ask the construction office before you start.
| The job | What the state code says |
|---|---|
| Inside the house | |
| Paint or wallpaper | No permit5:23-2.7(c)1i, iii |
| New flooring, any material | No permit5:23-2.7(c)1ix |
| Cabinets, built-ins, trim and moldings | No permit5:23-2.7(c)1vii, viii |
| Drywall or plaster on less than 25% of the wall area, one- or two-family home | No permitPaneling doesn't count as ordinary maintenance.5:23-2.7(c)1ii |
| Renovate or rearrange rooms in an existing one- or two-family home, with no primary structural member altered | Start on noticePermit first if it's a reconstruction: you can't stay in the work area, and it needs a new certificate of occupancy.5:23-2.17A(c)1ii |
| Remove or cut a load-bearing wall, beam or bearing support | Permit firstThe office can require engineered details.5:23-2.7(b)1, 2; 2.17A(c)1ii |
| Cut a new door or window opening, or resize one | Permit. Ask about noticePermit first if it alters a primary structural member.5:23-2.7(c)1v; 2.17A(c)1ii |
| Plumbing and appliances | |
| Swap a fixture for a similar one, with no change to the piping | No permit5:23-2.7(c)2x |
| Replace a faucet, valve or trap | No permit5:23-2.7(c)2vi, vii, ix |
| Refinish a tub or sink | No permitRelining a fixture is not ordinary maintenance.5:23-2.7(c)2ii |
| Replace a bath fan or kitchen range hood | No permitThe fan has to vent on its own to the outdoors. The hood can't exceed the old hood's rate unless it's 400 cfm or less, and it has to recirculate or vent on its own to the outdoors.5:23-2.7(c)3v, 5ix |
| Add fixtures in existing space, with no bigger water distribution system, water service or house drain | Start on notice5:23-2.17A(c)2 |
| Replace a water heater with one of like capacity | Start on notice5:23-2.17A(c)2 |
| Move a sink or gas line, or extend water or drain lines | Permit. Ask about notice5:23-2.7(b)6ii; 2.17A(c)2 |
| Electrical and heating | |
| Replace an outlet, switch or light with a like one | No permit5:23-2.7(c)3i |
| Add five or fewer outlets where the circuits or panel space and the service can carry the load, one- or two-family home | Start on notice5:23-2.17A(c)4 |
| Replace wiring with new wiring of the same capacity, one- or two-family home | Start on notice5:23-2.17A(c)4 |
| Replace a furnace, low-pressure boiler or air conditioner with one of like capacity | Start on notice5:23-2.17A(c)3 |
| New electrical service or panel | Permit firstIt's on neither the ordinary maintenance list nor the minor work list.5:23-2.7(b)6iii; 2.14(a) |
| Outside the house | |
| Re-roof a detached one- or two-family house | No permit5:23-2.7(c)1x |
| Replace siding on a one- or two-family house | No permitPolypropylene siding is the exception.5:23-2.7(c)1xi |
| Replace a window or door in the same opening, without changing its size or framing | No permitAn escape window or door can't lose required height, width or clear opening.5:23-2.7(c)1v |
| Repair or replace part of a deck, porch or stoop with matching material, in the same place | No permitNot where it holds up a roof or part of the building.5:23-2.7(c)1xiii |
| Build or fully replace a porch or stoop that holds up no roof or part of the building | Start on notice5:23-2.17A(c)1i |
| Build a new deck | Permit firstThe minor work list names porches and stoops, not decks.5:23-2.14(a) |
| Build an addition | Permit firstThe submission includes energy calculations.5:23-2.14(a); 2.15(f)1vi |
| Retaining wall 4 feet or higher, or shorter if it harms a foundation | Permit firstMeasure from the bottom of the footing, and add together all walls on the same slope.5:23-2.14(g) |
| Fence 6 feet or lower | No permitA barrier around a pool doesn't get this exception.5:23-2.14(b)9 |
| Shed up to 200 sq ft and 10 feet high, with no water, gas, oil or sewer connection | No permitWiring it still takes an electrical permit.5:23-2.14(b)8 |
| Demolish a building or structure | Permit first5:23-2.14(a) |
Before you rely on a “no permit” row
- Ordinary maintenance has limits. It never covers cutting away a load-bearing wall, removing or cutting a structural beam or bearing support, changing a required way out of the building, other work affecting structural or fire safety, or lead abatement (5:23-2.7(b)). The deck, porch and stoop row is the exception to the beam and structural-safety limits: repairing or replacing part of one with the same or closely similar material, in the same place, stays ordinary maintenance as long as it holds up no roof or part of the building (5:23-2.7(c)1xiii).
- The fence and shed rows follow a different rule. They are exemptions from the permit requirement itself (5:23-2.14(b)8 and 9), not ordinary maintenance, so the limits above don't decide them. Their limits are in their rows: no pool barriers for fences, and for a shed at a home, the size, height and utility limits, plus an electrical permit for any wiring.
- Zoning is separate, for every row. The table covers the construction code only. Zoning is your town's own rule, so a job that needs no construction permit can still need zoning approval. Bloomfield, for one, asks for a zoning permit for fences, sheds, driveways, walkways and retaining walls.
Which subcodes apply to your job
The application is one form, the F100, plus a technical section for each trade the job touches. The state says the nature of the project decides which sections apply.
| Subcode and form | What brings it in |
|---|---|
| Building, F110 | Footings, foundations, framing, roofs and interior or exterior finishes |
| Electrical, F120 | Wiring, outlets, fixtures, panels and service |
| Plumbing, F130 | Water and drain piping, fixtures, gas piping and gas equipment |
| Fire protection, F140 | Smoke and heat detection, alarms, sprinklers and suppression |
| Mechanical inspection, F145 | Heating and cooling equipment in one- and two-family homes |
A deck with no wiring is a building-only job. A kitchen that moves the sink and adds circuits brings in plumbing and electrical as well; our kitchen remodel cost guide works out what those permits cost in Belleville. An addition usually touches most of them. The application is filed with the construction official, or with that subcode official when the job involves only one subcode (5:23-2.14(a)). Which edition of the code the plans have to meet is a separate question, covered in our guide to the 2024 code change.

Who files: you or your contractor
Either. The owner can apply, or an agent, architect, engineer, licensed trade contractor or other contractor hired for the job (N.J.A.C. 5:23-2.15(d)). If someone other than the owner applies, an affidavit has to confirm the owner authorized the work. The permit stays the owner's property even when a contractor files.
- If a home improvement contractor does the work, its registration number goes on the application by the time work starts, and filing in the owner's name doesn't change that. A licensed electrician, plumber, architect or engineer working within that license gives its license number instead, and a few others that don't have to register, such as a home improvement retailer worth over $50 million, give none (5:23-2.15(b)9). Here's how to check that number.
- Plumbing, electrical and HVAC have to be done by licensed contractors, with the license number on the application and their seal and signature on that trade's form.
- Doing the work yourself: a single-family homeowner can do those trades on their own dwelling. The permit and inspections are the same.
- Plans carry the seal of a registered architect or licensed engineer, and licensed trade contractors can prepare plans under their own licensing rules. The construction official waives the seal for a single-family homeowner who drew the plans for their own detached house, with an affidavit.
- Your contract: a home improvement contractor can't start until it's sure the permits have been issued, and it owes you copies of the inspection certificates before final payment is due (N.J.A.C. 13:45A-16.2(a)10). A contractor who offers to skip the permit is offering to break that rule.
How to get one, and how long each step takes
- Get zoning and other approvals. No permit is issued until every required state, county and local approval is in place. For an addition or alteration to an owner-occupied one- or two-family home, plan review doesn't start until zoning approval is in (5:23-2.15(f)4ii), so the zoning time comes before the 20 days below.
- Fill out the forms. The state's forms page has the F100 application and the technical sections. You'll need the block and lot and the estimated cost of the work, which includes labor and materials, even ones you get for free. On paper, the state asks for one original and three photocopies of each form.
- Attach the plans, unless the office waives them. A paper filing needs at least two sets drawn to scale. For a single-family home the state lists what's enough: a site diagram, foundation and floor plans, elevations, a typical wall section, and the electrical, plumbing and mechanical details the work calls for. The construction official can waive plans when the work is of a minor nature (5:23-2.15(f)1x and 2.15A).
- File it, on paper or online. Every enforcing agency has to have a way to take applications and plans electronically (5:23-2.15B). The plan review fee is normally due when you file. Each town's office is on the state's roster of construction officials.
- Wait for the decision: 20 business days. The office has 20 business days to approve or deny an application, and a denial has to give its reasons in writing. Revised plans get an answer within seven business days. If the office says nothing by day 20, that counts as a denial so you can appeal to the Construction Board of Appeals. It is not an approval, and you can agree to more time.
- Pay, and keep the papers on site. The rest of the fee is due before the permit is issued. A copy of the permit stays on the job, and so does a set of the released plans. Give the construction official at least 24 hours' notice before work starts.
- Call for each inspection. Ask at least 24 hours ahead. The inspection happens within three business days of the time you asked for, or at another time within 30 days that you agree on. On a one- or two-family home, work stops until these are done, as they apply: footing trenches, foundation before backfill, utility services, then rough wiring, rough plumbing, framing and insulation. Work can't be covered before its inspection.
- Get the final inspection and the certificate. An addition gets a certificate of occupancy before it can be used. A renovation or alteration gets a certificate of approval. For minor work, the certificate of approval is based on what's visible at the inspection (5:23-2.17A(d) and 2.23).

Other clocks to know
- Emergency work not involving lead abatement can start right away. Give notice as soon as you can, and apply for the permit within 72 hours.
- A permit lapses if work doesn't start within 12 months of issue, or stops for six months after it starts.
- Three years: the construction official can revoke a permit if the project isn't finished by the third anniversary of issue. You can apply for a one-year extension, and the office can't unreasonably refuse it. The rule doesn't apply to interior work that can't be seen from outside, in a home where the permit holder lives; to a building whose exterior work and required site work are all finished; or to a project a mortgage lender has taken possession of (5:23-2.16(f)).
What a NJ construction permit costs
There is no statewide price. Each town sets its fees by ordinance, to cover what enforcing the code costs it, and has to keep the schedule posted and open to the public (N.J.A.C. 5:23-2.25 and 4.17). What the state sets is how the fee is built (5:23-4.18 and 4.19):
- Renovations, alterations and repairs are charged per $1,000 of estimated cost. Additions and new buildings are charged by volume.
- Plumbing, electrical and fire protection are charged by the fixture or device.
- Plan review is 5% to 25% of the permit fee. It's not refundable, and it comes off the permit fee when the permit is issued.
- A state surcharge goes on top: $1.90 per $1,000 of construction value, or $0.00371 per cubic foot for new buildings and additions.
Here is what that looks like in two Essex County towns, next to the state's own schedule. The state schedule applies only where the Department of Community Affairs is doing the enforcing or the plan review, so treat it as a yardstick.
| Fee | Belleville | Bloomfield | State schedule |
|---|---|---|---|
| Renovation, alteration or repair, per $1,000 of estimated cost | $28 | $39 to $50K $31 to $100K $25 above | $34 to $50K $26 to $100K $22 above |
| Addition or new building, per cubic foot | $0.038 | $0.040 | $0.038 |
| Each plumbing fixture | $15 | $25 | $15 |
| Outlets, switches and light fixtures | $50 for 1 to 6 $50 more for 7 to 50 | $90 for up to 20 $25 per 20 after | $50 for 1 to 50 $9 per 25 after |
| Plan review, share of the permit fee | 25% | 20% | 20% |
| Certificate of occupancy, one- or two-family home | $150 | $150 | $39 |
From Belleville Code § 12-1.3, Bloomfield Ordinance 25-12 (May 19, 2025) and N.J.A.C. 5:23-4.20, read November 8, 2026. Ask your town for its current schedule.
A worked example: on a $40,000 interior renovation, the building subcode line comes to $1,120 in Belleville and $1,560 in Bloomfield. The state surcharge adds $76 in either town, and plumbing and electrical are charged on top by the fixture. Small jobs hit a minimum, which is $85 for the building subcode in Belleville and $90 per subcode in Bloomfield.
If a project is abandoned, the fee for the work not done comes back, less any penalties. Plan review doesn't (5:23-2.27).
What happens if work was done without a permit
The penalty can reach $2,000 per violation, and for a missing permit the order to pay can issue as soon as the office finds it, with no time to fix it first (N.J.A.C. 5:23-2.31).
- Stop construction order. The town can halt the job in writing. Ignoring the order costs up to $2,000 per violation, and each day counts as a separate offense.
- The violation still has to be corrected. A notice of violation orders the correction, by a deadline in the notice.
- The owner is on the hook too. If the notice goes to your contractor, you get a copy and share responsibility for compliance, and the town won't issue a certificate of occupancy until a penalty is paid (5:23-2.30).
- It comes up when you sell. New Jersey's property condition disclosure form asks about additions and alterations by any present or past owner, and then whether the proper building permits and approvals were obtained.
If it's already done
Don't close up anything that's still open, because the code doesn't let work be covered before its inspection. Call the construction office, ask how it wants the application filed, and ask how it wants finished walls or ceilings handled. Then get the inspections and the certificate, so the file shows the work was approved.
Planning an addition or taking out a load-bearing wall?
Outside an emergency, both jobs need the permit before work starts, in every New Jersey town. Neither is ordinary maintenance or minor work: an addition is built to the rules for new buildings, and taking out a load-bearing wall alters the house's primary structure (5:23-2.7(b)1, 5:23-2.17A(c)1ii and 5:23-6.2(b)). On the jobs we build, we file the permits and meet the inspectors, in the town where the work is, across Essex, Union and Passaic counties. Our additions and structural work runs from plans to final inspection, including load-bearing walls and beams. We offer architectural drawings, and we also work with your own architect. What the wall itself costs, from the beam and the engineer to Belleville's permit fee, is worked out in our load-bearing wall removal cost guide, and building up a floor, with Belleville's height limit and its fee for an addition, in our second story addition cost guide.
Tell us the town, whether zoning is approved and whether plans exist. Those three answers set the order of the job. Work inside the house runs the same way: basement finishing and kitchen remodeling.

